One of the first questions every homeowner asks is: "How long will the hacking take?" It's a fair question — your entire renovation timeline depends on it. Your interior designer needs to know when the space is ready, your flooring contractor needs a clean slate, and you need to plan around the noise and dust.
The honest answer is that it depends on the scope, the property type, and how well the site is prepared. But after years of hacking walls and stripping out units across Singapore, we can give you realistic timelines — not vague guesses. Here's the breakdown.
Hacking Timelines by Scope
Not every hacking job is the same. A single partition wall and a full-unit strip-out are completely different animals. Here's what to expect for each scope:
| Scope of Work | Typical Duration | What's Involved |
|---|---|---|
| Single partition wall (non-load-bearing) | Half a day to 1 day | Setup, protection, hacking, debris bagging, basic cleanup |
| Multiple walls / layout reconfiguration | 1 to 3 days | Several partition walls, doorway openings, debris haulage |
| Kitchen strip-out (cabinets + tiles + backsplash) | 1 to 2 days | Cabinet dismantling, wall tile hacking, floor tile removal, debris clearance |
| Bathroom strip-out (tiles + sanitary ware) | 1 to 2 days | Sanitary ware removal, wall and floor tile hacking, debris haulage |
| Full unit strip-out (walls + floors + built-ins) | 3 to 5 days | All partition hacking, floor tile and screed removal, built-in dismantling, full debris clearance |
| Commercial reinstatement | 3 to 10 days | Partition walls, raised floors, ceiling grids, MEP isolation, full debris haulage |
Single Wall Hacking: Half a Day to One Day
Removing one non-load-bearing partition wall — say, to open up a kitchen or combine two bedrooms — is the most common hacking job. The actual demolition takes a few hours. The rest of the day goes into site protection, dust containment, hacking in controlled sections, bagging the rubble, and sweeping the workspace clean.
If the wall is brick (common in older HDB resale flats), it takes a bit longer than a drywall or stud partition (common in newer BTOs and condos). Either way, you should expect the crew in and out within a single working day.
Kitchen and Bathroom Strip-Outs: 1 to 2 Days
A kitchen strip-out involves more than just pulling out cabinets. The team has to isolate and cap off plumbing and gas lines, dismantle the carcasses carefully, hack the wall tiles and backsplash, and remove the floor tiles down to the screed. Done properly, that's a solid day to a day and a half.
Bathroom strip-outs are similar — sanitary ware comes out first, then wall and floor tiles are hacked, with care taken not to damage the waterproofing layer underneath if it's still within warranty. Plan for one to two days per bathroom.
Full Unit Strip-Out: 3 to 5 Days
A full-unit strip-out is the big one — every partition wall comes down, all floor tiles and screed are removed, built-in cabinets and wardrobes are dismantled, and the entire unit is cleared back to a bare shell. This is typically a three-to-five-day job depending on the unit size and how much built-in carpentry is involved.
The debris volume is significant — a full unit strip-out can generate enough rubble to fill dozens of heavy-duty waste bags. All of it has to be bagged, hauled to the lift lobby, transported down, and disposed of at NEA-licensed facilities. That haulage and disposal time is built into the schedule, not added on later.
Commercial Reinstatement: 3 to 10 Days
Reinstating a commercial space at the end of a lease is the most variable scope. It depends on the size of the unit, the extent of the fit-out that has to come out, and whether live services (data, power, sprinkler systems) need to be isolated by licensed trades before demolition begins. Small offices can be done in a few days; large retail or F&B reinstatements can run over a week.
What Can Slow Down a Hacking Timeline?
- Unapproved HDB or MCST permits — no permit, no work. We handle submissions, but approval takes 3 to 7 working days. See our HDB hacking rules guide for the full process.
- Poor site preparation — cluttered units take longer to protect and work in. Use our pre-hacking preparation checklist to get your site ready.
- Hidden utilities — embedded conduits or plumbing discovered mid-hack need to be isolated before work continues.
- Lift booking restrictions — condos and some HDB blocks require pre-booked lift slots for debris haulage, which can pace the job.
- Access issues — units far from the lift lobby or on floors with lift restrictions need more manual hauling time.
Permitted Working Hours: The Built-In Constraint
In HDB flats, hacking is only permitted from 9:00 AM to 5:00 PM, Monday to Friday — no weekends, no public holidays. That's a fixed eight-hour window per day, and it's non-negotiable. Condos may have their own MCST-imposed hours, sometimes even tighter.
This is why a job that looks like "two days of work" on paper might span three calendar days — the permitted hours are the real clock, not the raw labour hours.
How We Keep Your Timeline on Track
We give you a fixed schedule at the site assessment — not a vague estimate. That way your renovation contractor, your interior designer, and your post-renovation cleaning team can all plan around a concrete handover date.
Our quotes are itemised and transparent, so there are no surprises that stall the job mid-way. You can see typical pricing in our wall hacking cost guide. And every quote includes debris bagging, haulage, and NEA-licensed disposal — nothing is left in your unit for the next trade to work around.
Want a Fixed Timeline for Your Project?
The fastest way to get an accurate duration is to send us your floor plan or a few photos of the space on WhatsApp. We'll scope the works, confirm what can safely be hacked, and give you a fixed schedule and an itemised quote — usually within 24 hours.
Ready to lock in your hacking dates? Send your floor plan or photos and we'll give you a transparent, itemised quote with a fixed timeline.